Applicable scope:
Kindergarten, primary and secondary school playground, park trail, pedestrian bridge, runway, tennis court, basketball court, volleyball court, badminton court and other sports venues.
1、 Performance characteristics:
It is made by mixing high-strength, high elasticity, and strong ultraviolet resistant EPDM particles with a certain proportion of single component adhesive, and directly spreading and compacting it on a concrete or asphalt foundation. It has a long service life, elasticity, and dynamic design characteristics. The bottom layer is mixed with special adhesive particles in a controlled proportion using polyurethane adhesive, and then laid with thickness controlled by professional construction personnel. It is an alternative product for PU courts, with the advantages of convenient construction, strong adaptability to the foundation, and less prone to peeling and foaming.
1. 24H: Maintain a high level of quality in any season and temperature difference, and can be used after rain to improve utilization.
2. Good flatness: professional construction machinery construction Both thickness and flatness standards are required.
3. Moderate elasticity: The porous bottom layer has moderate elasticity and rebound, which can reduce physical exertion and increase competition results.
4. Impact resistance: With a strong and resilient buffer layer, it can absorb strong impact force, reduce sports injuries, and is suitable for long-term practice and competition.
5. Strong weather resistance: The special surface of the rubber particles can resist UV, ozone, wind and rain, as well as pollution from sulfite and gas, extending its service life.
6. Brilliant appearance: Colorful and beautiful, easy to maintain, saves management costs, and has high cost-effectiveness.
2、 Environmental protection EPDM floor mat pouring elastic floor construction process description:
The main raw materials for EPDM cast-in-place elastic flooring are adhesives and EPDM particles, and their product characteristics have strict requirements for the foundation bottom and construction process. The following points should be noted when using our company's products:
1、 Requirements for the bottom surface of the foundation:
1. Asphalt concrete or cement concrete can be used for foundation pavement, and it is required to have a certain strength and stability (cement concrete foundation needs to cut expansion joints, and waterproof layers may not be required).
2. Cracks and uneven frost heave caused by freezing are strictly prohibited in the foundation.
3. The foundation has good flatness and specified slope.
4. Flat surface Drainage.
5. The surface of the foundation should be kept clean and dry, and a strict maintenance period is required after the foundation is completed.
2、 Construction process requirements:
1. There are two construction processes for construction classification, mechanical paving and manual paving.
2. On the basis of meeting the requirements, surface pre-treatment should first clean the surface, and there should be no dirt, dust, water (including watermarks), oil stains, etc. After cleaning, evenly apply the primer on the foundation to enhance its bonding ability with the ground and avoid irreversible consequences.
3. Pay attention to the following issues when conducting small sample tests before construction
4. A: The usage of the material, such as material ratio and whether the curing time of the material is normal.
b: Afterwards, observe whether there is any loosening phenomenon and whether the adhesion, strength and other properties meet the requirements.
5. Preparation work before work (manual) materials, tools and equipment (clappers, rollers, soap water, cars, rakes, irons, mixers, etc.), auxiliary material preparation
6. Construction (manual): After mixing the materials in proportion, pour them into the site for paving, heat them with an electric iron (spray lamp heating) or pat them firmly with soap water, flatten the joints, and maintain overall flatness.
7. The required thickness of the site is 8mm for colored EPDM particles, and 5mm for EPDM colored particles. Or other requirements
8. Construction precautions (manual)
1) The optimal construction temperature for plastic is 15-35 ℃. If the temperature is too high or too low, it will affect the construction.
2) The paving tool used (commonly known as a trowel or push blade).
3) The mixing must be thoroughly and evenly mixed.
4) Each batch of materials must be well connected, otherwise there will be seams if the connection is not good.
5) When trimming, be sure to be neat.
6) Be sure to strictly follow the proportion of ingredients.
7) After the site is completed, check and clean the remaining items on the site to make the entire site beautiful.
9. After the completion of the site, communicate with Party A for acceptance and fill in the completion acceptance form. Construction evaluation form